Jay Clayton warns of more outages as the U.S. upgrades aging digital infrastructure

After network trouble reached 17 of 22 regional air traffic control centers, Senate Democrats asked the FAA to explain why backups could not restore normal service sooner.

Infraday News Desk · Based on official sourcesPublished
John F. Kennedy International Airport during the November 13, 2026 nationwide ground stop
JFK during the November 13, 2026 ground stop. Original photograph, displayed at web resolution. Sashimi-b / Wikimedia Commons, CC BY-SA 4.0 · Photo source

Director of National Intelligence Jay Clayton said on November 22 that Americans should expect more service interruptions as companies and government agencies upgrade the digital systems they rely on. Speaking to Dana Bash on CNN’s State of the Union, Clayton said some of that infrastructure has accumulated over three decades. Replacing it will require investment in both computing capacity and cybersecurity.

Clayton described a problem familiar to anyone who has waited for a system to come back online after scheduled maintenance. A company can tell customers when it intends to restore service, he said, only to discover during the work that it needs more time. Asked how the public should prepare, he emphasized keeping people informed. As The Hill reported, he compared the uncertainty to starting a home renovation and discovering unexpected work.

In aviation, the practical question is who decides when work can proceed on a network that controllers need around the clock. On November 13, a problem during routine equipment replacement disrupted air traffic across the country. The Federal Aviation Administration has since said it will reconsider when crews perform that work, including at smaller facilities far from the airports where travelers felt the delays.

How a maintenance job reached the departure board

The FAA traced the first signs of trouble to around 3:30 p.m. Eastern. Instability in its telecommunications network affected communications and radar information at 17 of its 22 regional air traffic control centers. The agency stopped departures nationwide. Controllers retained enough radio and radar coverage to bring about 3,500 aircraft already in the air safely to the ground. Flights resumed at 8:15 p.m., after the agency had observed the system operating reliably.

The FAA said it found no indication of a cyberattack. Its network provider, L3Harris, had been replacing equipment as part of the transition away from copper lines. In a November 17 update, Transportation Secretary Sean Duffy said investigators had reproduced the behavior they saw during the outage. At the time of that briefing, they still had to determine why it happened.

What senators want to know before the next installation

In a November 16 letter, Senate Commerce Committee Democrats led by Sen. Maria Cantwell of Washington described the scale of the work already underway. Citing figures from L3Harris, they said the transition involved converting more than 3,600 routers. About 400 new devices had been installed, of which 69 were operational. A sample had passed testing before deployment. The senators asked whether those tests adequately reflected the conditions the equipment would encounter in service.

The timing of the work matters for airport operators and airlines. The FAA said major facilities typically schedule maintenance at night, when traffic is lighter. Crews had routinely performed replacements at remote facilities during the day. A decision about a maintenance window at one location could therefore affect departure schedules at airports across the country.

Congress is also weighing how much to spend on a broader overhaul of air traffic control. On November 17, Duffy and FAA Administrator Bryan Bedford made the case for roughly $50 billion in additional funding. Congress had already appropriated $12.5 billion in July 2025. In a September review, the Government Accountability Office found that the FAA lacked a cost estimate covering the whole program and an integrated schedule for its first phase. Those gaps make it harder to judge the cost and timing of keeping existing equipment in service while replacements come online.

For operators waiting on replacement equipment, the immediate question is what the FAA will require before another batch goes into service. The senators asked the agency to assess devices already operating and explain why backup arrangements could not restore normal service sooner. An answer would help airports distinguish the precautions they can take locally from decisions that depend on the national network.

Have a correction or information about this story? Contact Infraday.

Senate Commerce Committee Democrats asked for information by November 23 and requested a joint technical briefing with the FAA, L3Harris and equipment supplier Juniper.

Review the official next step →

Infraday+ research

Federal Aviation Administration

The FAA oversees the air traffic network and the modernization program examined in this story.

Primary sources

You’re offline. Reconnect to load the latest Infraday updates.