AI Infrastructure · Great Britain

AI builders lock in memory as Britain weighs a price for holding grid capacity

A proposed grid fee could put £23.75 million to £71.25 million at stake for a 100 MW campus, even as projects already under construction secure chips for 2027.

Infraday News Desk · Based on official sourcesPublished
A speaker stands at a University of Bristol lectern beside a screen labeled Isambard-AI.
A speaker at the July 17, 2025 launch of the University of Bristol’s Isambard-AI supercomputer. Alecsandra Dragoi / DSIT, via UK Government (cropped), CC BY 4.0 · Photo source

Most AI data centers due in 2027 are already under construction, and buyers have secured much of the high-bandwidth memory they will need, according to TrendForce’s November 18 market bulletin. Britain’s energy regulator faces a different problem. Developers have reserved so much grid capacity that Ofgem wants them to show who will use their facilities and what equipment they have ordered before they can keep their place in line.

The two findings describe different stages of a build. A server manufacturer can have firm orders for memory going into facilities under construction this year. A network planner looking several years ahead still has to decide which proposed campuses will draw power, how much they will need in the first phase and when to have a substation ready.

What Britain’s 125 GW figure measures

Between November 2024 and June 2025, the capacity covered by contracted offers to connect electricity users to Britain’s grid rose from 41 gigawatts to 125 GW, according to Ofgem. The total covers multiple industries. Data centers accounted for much of the increase. The figures tell a network operator how much capacity developers have sought to reserve. Actual electricity use begins when a facility connects and its customers start running equipment.

Ofgem’s July proposal would require large data center developers to put up £237,500 to £712,500 per megawatt when accepting a connection offer. A developer would recover the security when the project connects and could forfeit it by leaving the queue early. At a hypothetical 100 MW campus, the proposed range works out to £23.75 million to £71.25 million. The amount at risk would give a developer a financial reason to size its request closer to what it expects to build.

The regulator also proposed checking for a credible customer, evidence that the developer can finance and deliver the project, and orders for electrical equipment with long lead times. Switchgear is one example. A purchase order for the equipment that will control power flowing into the first data hall gives the network operator something it can check against the developer’s timetable.

Why memory buyers are already committing

Memory suppliers see demand earlier in the construction cycle. TrendForce found that contract prices for conventional DRAM, the working memory used in servers and other devices, rose roughly 93% to 98% in the first quarter of 2026 compared with the previous quarter. Suppliers favored server customers as cloud companies competed for capacity. The price increase was for conventional DRAM. High-bandwidth memory, which feeds data rapidly to AI processors, is a separate product with its own supply contracts.

By November, TrendForce saw new production capacity coming online and manufacturers shifting to processes that yield more memory per wafer. It still expected AI construction already underway to keep supplies tight, even as it forecast smaller contract price increases in successive quarters. For a contractor pricing a data hall, those findings help explain why a customer might lock in servers well before the building is ready to take delivery.

A completed installation shows what those early orders can eventually produce. The University of Bristol’s £225 million Isambard-AI supercomputer launched in July 2025 at the Bristol and Bath Science Park with 5,400 Nvidia GH200 chips. Its operator, site and installed equipment were all identifiable at launch. A campus proposed in a connection queue may still be years away from having comparable evidence for its first phase.

The decision developers are waiting for

Developers of multiphase campuses raised a timing problem in the UK government’s consultation. They asked officials to account for how large projects progress in stages. A site can have a credible first tenant while its later buildings remain unleased. The size and timing of any required security will matter to owners deciding how much power to reserve for those later phases.

The government expects Ofgem to issue its decision in the first quarter of 2027, ahead of the National Energy System Operator’s next application window. That decision should tell developers how much security to provide and what evidence network companies can require before they continue holding capacity for a project.

Have a correction or information about this story? Contact Infraday.

The UK government expects Ofgem’s decision on data center queue rules in the first quarter of 2027.

Review the official next step →