Rail & Transit · Los Angeles County, California

LA Metro staff seek $29.6 million to bring Sepulveda rail design to 30%

The proposed contract change would update cost estimates and determine how to divide construction work on the Valley-to-Westside rail line.

Infraday News Desk · Based on official sourcesPublished
Metro’s G Line Sepulveda bus stop and shelter in Los Angeles.
The temporary Sepulveda stop on Metro’s G Line in September 2026. The proposed rail corridor would connect with the G Line at Van Nuys Boulevard. RobotGoggles / Wikimedia Commons, CC BY-SA 4.0 · Photo source

Los Angeles County Metropolitan Transportation Authority staff put a $29.6 million modification to the Sepulveda Transit Corridor Partners contract on the Executive Management Committee’s November 19 agenda. The proposal would take engineering from roughly 15% to 30% design for the planned underground rail connection across the Santa Monica Mountains.

If authorized, the change would bring the value of the existing technical-services contract from about $87.4 million to $117 million. Staff separately requested a $26.5 million increase in the project’s fiscal 2027 non-labor budget. The $29.6 million would pay for a change to the team’s contract. The $26.5 million would raise this year’s approved non-labor spending on the project to $85.5 million.

The first segment narrows the design questions

Metro’s board selected an underground heavy-rail route in January. The preferred route runs from the Van Nuys Metrolink station to the E Line at Expo/Sepulveda. The board also identified a shorter segment that could open first, roughly 8.4 miles between the G Line at Van Nuys and the D Line at Wilshire/Westwood.

The design team would refine the work packages, revisit the cost estimate and financial plan, and examine how to bring construction contractors into the design process early. These choices matter to future bidders because they determine which pieces of the railway one contractor would deliver and where its responsibilities would meet another contractor’s work.

Metro wants competing contractors to help design their portions of the railway before preliminary engineering is complete. The agency would seek a fixed price for each package as the designs mature. Staff say they would come back to the board for authority to pay for that early contractor work, including participation by small businesses.

The proposed engineering budget draws on the Measure R and Measure M transit construction funds. Those revenues are restricted to capital work. Staff are also asking for about $3 million in authority for future contract changes so the design team can respond if an assumption changes. That authority is a separate decision from approving the engineering fee.

Metro tentatively expects to bring a public-private partnership business case to the board in 2027. That analysis would help the board decide whether to pursue a formal partnership. In the meantime, the design team would coordinate with the Los Angeles Department of Water and Power, UCLA and local governments while federal and state environmental review proceeds.

A separate public decision is approaching. Metro is accepting environmental scoping comments through November 23 on issues including station locations and a maintenance and storage site. The November committee file records a staff request. A recorded board action and an executed modification would establish the status of the additional engineering work.

Key details

Proposed contract modification
$29.6 million

Metro lists November 23 as the deadline for scoping comments. Check the committee’s record for final action on the proposed design-contract modification.

Review the official next step →