FAA investigates router replacement after nationwide ground stop
Duffy says investigators are reviewing a router and its installation after work on the FAA’s legacy network preceded the November 13 disruption. The root cause remains under investigation.

Updated November 16, 2026: Added Duffy’s account of the maintenance work, laboratory investigation and precautionary router changes.
Transportation Secretary Sean Duffy says investigators are examining a router and its installation after maintenance on the FAA’s legacy telecommunications network preceded the November 13 nationwide ground stop.
In a November 15 update, the agency said excessive connection attempts disrupted aircraft communications and radar information. Its initial investigation identified a radar location in Amarillo, Texas, and a radio communications site in El Dorado, Arkansas, as potential sources of the traffic.
The FAA said L3Harris had been installing a router at the Arkansas site. Blocking both locations stabilized the network. The root cause remains under investigation.
In a November 15 account published by the Transportation Department, Duffy said work in El Dorado involved replacing an obsolete copper line scheduled for disconnection. When the new router was activated, equipment in Amarillo that had been replaced about three weeks earlier also began flooding the network, he said.
The router was sent to an L3Harris laboratory in Florida for examination with FAA staff. Duffy said investigators were reviewing both the equipment and the installation process. That account describes the investigation’s focus, rather than a completed finding of fault.
The FAA says it disabled the same broadcasting functionality on approximately 60 similar routers as a precaution.
A network-wide disruption
Instability affected 17 of 22 Air Route Traffic Control Centers and several terminal facilities. Some frequencies and radar feeds remained available. Air traffic resumed at 8:15 p.m. Eastern on November 13.
The FAA reported no indication of a cyberattack and plans to reassess the timing of remote-site maintenance.
The planning problem predates the outage
A September GAO report found the FAA’s first modernization phase had 11,389 separate project schedules without an integrated master schedule. That created a risk of overlapping installations at individual sites without adequately coordinating their effects on controllers. GAO recommended a reliable lifecycle cost estimate and a detailed integrated schedule.
Those findings identify program risks; they do not establish what caused this particular incident.
Infraday perspective: Replacing obsolete communications equipment is only one part of renewal. The transition also depends on testing, isolation of failures, coordination among contractors and workable maintenance windows. The investigation’s findings will matter for how the FAA organizes that work across a live national system.
The immediate next step is a substantiated root-cause finding and the resulting corrective measures. Lifting the ground stop and completing that investigation are separate milestones.
Photo: Sashimi-b / Wikimedia Commons, CC BY-SA 4.0. JFK during the November 13, 2026 ground stop. Original photograph, displayed at web resolution.
Additional coverage: TechCrunch’s November 14 report.
Why it matters
System renewal depends on coordinated installation, maintenance windows and failure isolation across a continuously operating air traffic network.
Status and next steps
FAA and L3Harris continue the root-cause investigation; FAA says it will reassess the timing of remote-site maintenance.
Review the official next step →Project contacts and next steps
A direct project contact has not been verified for this article. Consult the linked source organization for the appropriate office.
Primary sources
- FAA: ground-stop questions and answers · 2026-11-15
- GAO: modernization cost and schedule review · 2026-09-14
- USDOT: Duffy’s investigation update · 2026-11-15