Roads & Bridges
Addison Advances Keller Springs Utilities and Westbound Roadway Work
Addison’s Keller Springs Road project is advancing utility installation and westbound roadway preparation between Quorum Drive and the Dallas North Tollway.
Addison, Texas, is advancing utility and roadway work on the Keller Springs Road reconstruction between the Dallas North Tollway and Addison Road. The town’s latest project update says crews are forming the westbound roadway between Quorum Drive and the tollway for reinforcing steel and concrete paving, subject to weather and field conditions.
Water-line installation is approximately 85% complete and sanitary-sewer installation about 75% complete, according to the official project page. Coordination is also continuing on Oncor manhole adjustments ahead of paving. The Keller Springs Road/Addison Road intersection remains open, with traffic control and access monitored through the construction area.
The town’s earlier construction-award material identified Tiseo Paving as the proposer on a base construction proposal of about US$16.61 million, but this status update is a construction milestone rather than a new contract award. Current completion timing was not stated in the reviewed update.
Official Addison project page. Source reviewed October 23, 2026.