Data Centers & Digital Infrastructure · Eastern Kentucky
TeraWulf Contracts 1 GW for Muskie Campus, Targets Second Phase in 2029
The amended power agreement advances planned delivery; regulatory approval and utility construction remain conditions.
TeraWulf executed an amended electric-service agreement with Kentucky Power that doubles contracted power at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW, the company announced October 5.
The first 500 MW phase remains targeted to begin ramping in 2028. Planned delivery of the second phase moves from 2030 to 2029, subject to Kentucky Public Service Commission approval and the utility’s construction schedule.
Kentucky Power is developing a 765-kV/345-kV substation connected to the regional transmission network. Contracted power is not energized IT capacity. TeraWulf is also evaluating a possible 2 GW campus, which remains dependent on further planning, infrastructure and agreements.
TeraWulf announcement — October 5, 2026 · TeraWulf profile. Source checked: October 13, 2026.
Key details
- Contracted power
- 1 GW
- First phase target
- 500 MW beginning to ramp in 2028
- Second phase target
- 500 MW planned for 2029
Why it matters
The amended service agreement increases contracted power and advances the second phase, but contracted power is not energized IT capacity and regulatory and utility milestones remain.
Status and next steps
The first 500 MW phase is targeted to begin ramping in 2028; the second 500 MW phase is planned for 2029, subject to Kentucky Public Service Commission approval and Kentucky Power construction.
Review the official next step →Project contacts and next steps
A direct project contact has not been verified for this article. Consult the linked source organization for the appropriate office.
Primary sources
- TeraWulf announcement · 2026-10-05
- TeraWulf SEC exhibit · 2026-10-05