Data Centers & Digital Infrastructure · Eastern Kentucky

TeraWulf Contracts 1 GW for Muskie Campus, Targets Second Phase in 2029

The amended power agreement advances planned delivery; regulatory approval and utility construction remain conditions.

Infraday News Desk · Based on official sourcesPublished

TeraWulf executed an amended electric-service agreement with Kentucky Power that doubles contracted power at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW, the company announced October 5.

The first 500 MW phase remains targeted to begin ramping in 2028. Planned delivery of the second phase moves from 2030 to 2029, subject to Kentucky Public Service Commission approval and the utility’s construction schedule.

Kentucky Power is developing a 765-kV/345-kV substation connected to the regional transmission network. Contracted power is not energized IT capacity. TeraWulf is also evaluating a possible 2 GW campus, which remains dependent on further planning, infrastructure and agreements.

TeraWulf announcement — October 5, 2026 · TeraWulf profile. Source checked: October 13, 2026.

Key details

Contracted power
1 GW
Second phase target
500 MW planned for 2029

Why it matters

The amended service agreement increases contracted power and advances the second phase, but contracted power is not energized IT capacity and regulatory and utility milestones remain.

Status and next steps

The first 500 MW phase is targeted to begin ramping in 2028; the second 500 MW phase is planned for 2029, subject to Kentucky Public Service Commission approval and Kentucky Power construction.

Review the official next step →

Project contacts and next steps

A direct project contact has not been verified for this article. Consult the linked source organization for the appropriate office.

Primary sources

Explore in Infraday+

TeraWulf organization record →

You’re offline. Reconnect to load the latest Infraday updates.